This was a gym construction in which I did the majority of the work and the owner pitched in or used friends for certain things he could get done at the friend price.
Here is a picture of day 1. Someone else did the demo and we just showed up to take a look around.
Our starting point was to get some underground plumbing done. We had an existing nearby restroom and are merely moving it over about 25 feet.
We had to relocate some mechanical lines. Material was delivered right away as well.
Here we had some windows being covered by a wall. So we painted some drywall black and attached it into the window frame to obscure the view from outside.
After we reworked the mechanical and poured the underground we started framing.
Here the panel has a bunch of new electrical runs hanging from as we still work.
After we double drywall and insulate we are spraying some texture. Some walls are fire tape only because they will be covered with wood.
Don’t forget to patch the roof!
The owner and his buddies put in a lot of the finishes such as the high bay lighting, the foil, the paint and the wood. Which is fine with me. Here is the finished product. I think it looks great.
s the finished product. I think it looks great.